Heat Network Registration: What Landlords Must Do by 26 January 2027

Landlords who run communal heating for flats may be heat network operators or suppliers. Existing networks must be registered with Ofgem by 26 January 2027.

Never miss a renewal

LLCR tracks your compliance deadlines and reminds you before they expire. One place for your whole portfolio.

Track your first property free

No payment card. First property stays free.

Ofgem has regulated communal and district heat networks since 27 January 2026 under the Heat Networks (Market Framework) (Great Britain) Regulations 2025. Anyone already operating or supplying one must register it with Ofgem by 26 January 2027. For landlords, that can include a building of flats sharing one heating system, but not most shared houses.

This article is for general information purposes only and does not constitute legal advice. Landlords should seek independent legal advice for their specific circumstances. It describes the position in England.

What is a heat network, and is my rental property on one?

A rental property is on a regulated heat network if heating, cooling or hot water reaches it from a shared source serving more than one separate home or building. The Regulations apply across Great Britain, and only "relevant" heat networks are regulated. Ofgem's registration guidance, relying on section 216 of the Energy Act 2023, describes two main types:

  • a communal heat network, meaning one that supplies heating, cooling or hot water to a single building divided into separate premises, such as a block of flats with a central boiler room; and
  • a district heat network, meaning one that supplies two or more buildings.

A flat with its own boiler that heats only that flat is not a communal or district network, because there is no shared system serving separate premises. The common landlord set-ups line up like this:

Set-upLikely positionSource
Flat or house with its own boiler serving only that homeNot a communal or district heat networkEnergy Act 2023 s.216, as described in Ofgem guidance
Block of flats with a central boiler or plant room supplying the flatsCommunal heat network, in scopeOfgem registration guidance, paras 2.24 to 2.26
Shared plant supplying two or more buildingsDistrict heat network, in scopeOfgem registration guidance, para 2.20
A single shared house HMO with one heating systemExemptRegulation 13(2)(a)
Section 257 HMO (a converted block of self-contained flats) with shared heatingNot covered by the HMO exemption, may be in scopeOfgem registration guidance, para 2.33
A single converted building with one source appliance of 45kW thermal or lessExemptRegulation 13(2)(b)

How the HMO exemption works

Regulation 13(2)(a) exempts a network that only serves a single house in multiple occupation, defined by reference to paragraphs (a) to (d) of section 254(1) of the Housing Act 2004. Ofgem explains that a shared house with a shared kitchen or bathroom is not divided into separate premises, which is why it falls outside. Our guide to HMO management regulations covers the separate duties on water, gas and electricity supply that apply in most HMOs (other than section 257 converted blocks).

The exemption does not reach section 257 HMOs, the converted blocks of self-contained flats described in section 254(1)(e). Ofgem states that these may be relevant heat networks if supplied by a shared system.

The 45 kilowatt conversion exemption

Regulation 13(2)(b) exempts a network that only serves a single converted building, as defined in section 254(8) of the Housing Act 2004, and has no more than one source appliance with a capacity of no more than 45 kilowatts thermal. A source appliance, meaning under regulation 13(5) an appliance whose main purpose is to heat or cool the liquid or gas that is distributed in the network, is usually the boiler or heat pump. A converted house split into three flats and run from one domestic-sized boiler is the typical case. Two boilers, or one larger plant, takes the building outside this exemption.

Am I the heat network operator or the supplier?

A landlord can be the operator, the supplier, both, or neither, depending on who controls the system and who deals with residents about heat. Regulation 13(3) treats a person as operating a network if they control the transfer of thermal energy on it for the purpose of supplying heating, cooling or hot water. Ofgem's guidance describes the supplier as the person responsible for the commercial arrangements with customers, including setting charges, issuing bills, customer service and handling complaints.

In leasehold blocks, Ofgem's guidance states that the operator is typically the freeholder, but that a Right to Manage company or a residents' management company may take that role depending on how the building is run. Ofgem asks every party to assess its own position against the definitions rather than assuming.

Your situationLikely roleWhat to check
You own a whole building of flats and run its communal heatingProbably operator, and supplier if you charge occupants for heatWhether an exemption applies; whether a managing agent acts for you
You let one leasehold flat in a block with communal heatingThe freeholder or management company is typically the operatorYour lease and service charge terms; ask the freeholder what they have registered
Your tenants have their own heat supply contract with an energy company or heat supplierUnlikely to be operator or supplierConfirm the contract sits with the tenant, not with you

Ofgem's registration guidance does not say whether a buy-to-let landlord who passes a share of communal heating costs on to a tenant is a supplier. Its consumer protection guidance recognises that heat can be supplied under a tenancy or lease, or included in rent or service charges, but it does not settle who the supplier is in that situation. The answer will depend on the arrangements, so landlords in that position are advised to check with the freeholder and, if still unclear, with Ofgem or a solicitor.

What does registration involve, and when is the deadline?

Existing operators and suppliers must register each relevant heat network through Ofgem's digital service by 26 January 2027. Under regulation 27, anyone carrying on a regulated activity before that point is treated as already authorised, known as deemed authorisation, so no application is needed. Registration is a separate duty imposed by authorisation condition A4.

The date comes from the Regulations themselves. Regulation 2 fixes the launch date as 27 January 2026, and regulation 26 ends the "first part of the initial period" on the day before its first anniversary, which is 26 January 2027. Ofgem's registration guidance refers to 27 January 2027 in places, while its web pages give 26 January. Registering well before either date avoids the question. Regulation 26(2) allows Ofgem to extend this period with the Secretary of State's consent, but no extension had been announced at the time of writing.

Ofgem's registration guidance explains that the operator starts the registration and the supplier then completes its own section once invited. The information requested includes:

  • details of the organisation, its structure and financial resilience indicators;
  • the regulated activities carried out on the network;
  • the network type, location, number of buildings, energy source and heating capacity;
  • customer numbers by type, and whether any are in a vulnerable situation;
  • confirmation that a continuity plan and a complaints procedure are in place; and
  • a declaration about people with significant managerial responsibility or influence.

Registration is not an approval process. Ofgem's guidance states that once the submission is complete, an email confirmation with a unique ID is issued for each network. Keep that confirmation with the property's records, alongside the other documents in our record retention table.

What happens if I miss the deadline?

Failing to register is a breach of authorisation condition A4, which Ofgem can enforce. Regulation 31 allows Ofgem to impose a financial penalty for a breach of an authorisation condition, and regulation 37 allows a consumer redress order where residents have suffered loss, damage or inconvenience. Under regulation 45, the combined amount must not exceed 10% of turnover or £1 million, whichever is higher.

Ofgem's penalty policy says it will take account of seriousness, remedial steps and prompt self-reporting when setting any penalty. Whether Ofgem takes action in a particular case, and at what level, is a matter for Ofgem and depends on the facts.

Two further points matter:

  • Any regulated activity that begins after 26 January 2027 cannot rely on deemed authorisation, which only covers activity started before then. Ofgem says new activity will need authorisation by application.
  • The consumer protection conditions, covering matters such as billing, back-billing, complaints and support for residents in vulnerable situations, came into effect on 27 January 2026. Ofgem's guidance states they apply both before and after registration.

How does this fit with a landlord's other duties?

Heat network regulation sits alongside a landlord's existing obligations rather than replacing them. A communal boiler serving rented flats still raises questions under gas safety law, the HHSRS and, for HMOs, licensing conditions. Our complete landlord compliance checklist sets out the full set of duties for a let property in England, and the guide to the mandatory HMO licensing threshold helps confirm what kind of HMO a building is before relying on the heat network exemption.

What should a landlord do before 26 January 2027?

  1. Check whether any let building has a shared heating, cooling or hot water system serving separate flats or more than one building.
  2. Test each one against the exemptions in regulation 13(2): a single HMO within section 254(1)(a) to (d), or a single converted building with one source appliance of 45kW thermal or less.
  3. Work out who the operator and supplier are, using the lease, any management agreement and any Right to Manage or residents' management company arrangements.
  4. If you are a leaseholder landlord, ask the freeholder or managing agent in writing what has been registered, and keep the reply.
  5. If you are the operator or supplier, create an account on Ofgem's heat networks registration service and nominate a regulatory contact.
  6. Put a continuity plan and complaints procedure in place, then submit the registration and file the confirmation ID.
  7. Take legal advice where the roles or the exemptions are unclear.

Keeping the heat network record with the property

The LLCR platform is designed to hold this kind of evidence against each property. A landlord can record the registration deadline in compliance tracking with a reminder well before 26 January 2027, then store the Ofgem confirmation ID, the freeholder's written reply, the continuity plan and the complaints procedure in the document vault. If a resident complains or Ofgem asks questions, the dated record shows what was in place and when. LLCR is free for one property.

Official sources: Heat Networks (Market Framework) (Great Britain) Regulations 2025, regulation 13, Ofgem: who should register, Ofgem registration guidance and Ofgem penalty policy.


Not sure which compliance duties apply to each of your lets? The free LLCR compliance checker takes a few minutes and shows where each property stands.

Frequently asked questions

Does a landlord with a block of flats and one shared boiler need to register with Ofgem?

Usually yes, if the boiler supplies heating or hot water to flats that are separate premises in one building, because that is a communal heat network. The main exception is a single converted building served by one boiler or other source appliance of no more than 45 kilowatts thermal, which regulation 13(2)(b) of the Heat Networks (Market Framework) (Great Britain) Regulations 2025 takes out of scope. Existing networks must be registered by 26 January 2027.

Is an HMO with a shared boiler a heat network?

Where the heating system serves only a single HMO within section 254(1)(a) to (d) of the Housing Act 2004, it is exempt under regulation 13(2)(a), so a typical shared house with one heating system does not need registering. An HMO flat inside a larger block on communal heating is not covered, because that network serves the whole building. A section 257 HMO, meaning a building converted into self-contained flats, is not covered by that exemption and may be in scope unless the 45 kilowatt converted building exemption applies.

What happens if a heat network is not registered by 26 January 2027?

Registration is required by authorisation condition A4, so missing the deadline is a breach that Ofgem can enforce. Under regulation 31, Ofgem can impose a financial penalty and, under regulation 37, make a consumer redress order where residents have suffered loss, damage or inconvenience. Under regulation 45, the penalty and any compensation for a contravention are capped at 10% of turnover or £1 million, whichever is higher. The consumer protection conditions on billing and complaints have applied since 27 January 2026 whether or not the network is registered.

This article is provided for informational purposes only and does not constitute legal advice. LLCR is a compliance management platform, not a law firm. For advice specific to your situation, consult a qualified solicitor.